Finance Company / London Bridge

Project Size: 5,000 sq ft.

Duration of Project : 8 weeks

This was a 5000 sq ft 8 Week project in London Bridge within an existing listed building

This was a CAT B fit out in which CBL were responsible for the design, install & commissioning of the following systems.

Due to the status of the building and the lack of ceiling and floor depth all services had to be installed surface in galvanised containment and set out to ensure it was aesthetically pleasing for the client

  • Underfloor Power Track
  • Desk Power
  • Lighting Installation
  • Lighting Control
  • Emergency Lighting
  • Leak Detection System
  • Access Control System
  • Data Wiring & Installation
Related projects
Finance Company / London Bridge

Project Size: 5,000 sq ft. Duration of Project : 8 weeks

Continue reading

Communications Company – Slough, West London

Project Size: 10,000 sq ft. Duration of Project : 12 weeks

Continue reading

Kay & Co. Paddington London

Project Size: 680 m sq. Duration of Project : 12 weeks

Continue reading


Corney & Barrow / Masons Avenue

Project Size: 5,286 sq ft. Project Value: £160K Duration of Project : 10 weeks

Continue reading

Corney & Barrow / Waterloo Cabin

Project Size: 1,582 sq ft. Project Value: £90K Duration of Project : 10 weeks

Continue reading

Sandwich / Putney

Project Size: 9,000 sq ft. Duration of Project : 12 weeks

Continue reading


K&K Hotel / Earls Court

Duration of Project : 20 weeks

Continue reading