Brioni / Bruton St, London

Project Size: 9,000 sq ft.

Duration of Project : 24 weeks

This 9,000 sq ft project was carried out over 24 weeks in five Separate phases over 6no. Floors due to the client’s requirements to continue trading.

The store was completely re-wired from top to bottom and CBL were involved in the design process. The systems covered in this install were as below;

  • Distribution & Metering
  • Lighting Install & Lighting Control System
  • Emergency Lighting
  • Small Power
  • Data Install
  • CCTV / Intruder Alarm / Access Control
  • Fire Alarm System
Related projects
Brioni / Bruton St, London

Project Size: 9,000 sq ft. Duration of Project : 24 weeks

Continue reading

M&M World / London

Project Size: 35,000 sq ft. Project Value: £1.3M Duration of Project : 20 weeks

Continue reading

Anthropologie Flagship Store / Regents St

Project Size: 1,296 sq ft. Project Value: £350K Duration of Project : 16 weeks

Continue reading


Polo Batavia / Holland

Project Size: 15,000 sq ft. Duration of Project : 12 weeks

Continue reading

Urban Outfitters / Brighton

Project Size: 13,000 sq ft. Project Value: £255K Duration of Project : 20 weeks

Continue reading

Kid Robot / London

Project Size: 1,160 sq ft. Duration of Project : 20 weeks

Continue reading


Hermes / Glasgow

Duration of Project : 15 weeks

Continue reading

Hoopers / Carlisle

Project Size: 8,000 sq ft. Duration of Project : 20 weeks

Continue reading

Amouage / London

Project Size: 750sq ft. Project Value: £25K Duration of Project : 6 weeks

Continue reading


Anthropolgie / Kings Road

Project Size: 750sq ft. Project Value: £350K Duration of Project : 16 weeks

Continue reading